Federal Highway Construction in Downtown Boca Raton: What Changes

The Florida Department of Transportation's work on U.S. 1 through downtown Boca Raton covers 1.3 miles, from Camino Real to NE 8th Street and Mizner Boulevard. Northbound traffic on the southern part of that stretch is already down to a single lane. FDOT will make a smaller version of that squeeze permanent. Between Camino Real and SE 5th Street, the state is removing the 11-foot outside lane in each direction and using the space for separated bike lanes and 11-foot sidewalks. North of SE 5th Street, near Mizner Park, the street keeps its lane count. Construction is scheduled to run through late 2027. For that whole period, the southern approach is where downtown driving gets harder, and the northern end, where most of this fall's downtown calendar takes place, has tighter limits on when lanes can close.

Two different streets inside one contract

FDOT's project page splits the corridor at SE 5th Street and Mizner Boulevard. The two halves end up looking different, and each has its own rules for closures during construction.

Camino Real to SE 5th St/SE Mizner Blvd SE 5th St/SE Mizner Blvd to NE 8th St/NE Mizner Blvd
Travel lanes before the project Three each way Two each way
Travel lanes after completion Two each way Two each way
What gets added Separated bike lanes, 11-foot sidewalks Separated bike lanes from a narrower median
Single-lane closures Allowed in either direction, no time limits Northbound 7:30 p.m. to 8 a.m.; southbound 7:30 p.m. to 11:30 a.m.
Two-lane closures Non-peak hours on non-event days. Northbound 10:30 a.m. to 4:30 p.m. and 6:30 p.m. to 7:30 a.m.; southbound 7:30 p.m. to 12:30 p.m. No windows listed by FDOT

On the southern segment, a lane can be closed at any hour. On the northern segment, the single-lane closure windows FDOT lists fall in evenings and mornings. In both halves, FDOT says access to businesses and residences will stay open and the speed limit will remain 35 mph. FDOT lists General Asphalt Company as the contractor and puts the estimated construction cost at $6.3 million.

The southern stretch is already down to one northbound lane

Work started in late August. First, the inside northbound and southbound lanes between SE 8th Street and SE 5th Street closed from August 24 through September 11, The Coastal Star reported. The current phase hits northbound traffic harder. BocaNewsNow's September 27 traffic roundup lists northbound U.S. 1 between Camino Real and SE 5th Street at one lane through October 16. It also lists intermittent closures of one northbound and one southbound lane at Camino Real from 8:30 a.m. to 4 p.m. through Friday, October 2, for signal work.

That signal work at Camino Real is part of the permanent design. FDOT is replacing the traffic signals there with mast arms and adding a second left-turn lane for northbound Federal drivers turning onto Camino Real. The state says the extra turn lane will improve the intersection's operations and capacity. This is the corridor's southern gateway, near the Boca Raton resort at 501 East Camino Real. Today it carries the most construction disruption. Once the work is done, it is the one place in the corridor that gains lane capacity.

The single northbound lane south of SE 5th Street is temporary, but the reduced lane count is not. When the project wraps up, that same stretch will have two lanes each way instead of three. North of SE 5th Street, the bike lanes come from narrowing the median, so drivers keep the lanes they have now.

Why the outside lane is the one going

The design has been discussed in public for two years. At a September 2024 City Council workshop, FDOT presented a plan to cut the six-lane section between Camino Real and SE Mizner Boulevard to four lanes. The proposal at the time used a two-foot striped buffer next to the bike lane. Council members pushed for physical separation instead.

"A bike lane is not a bike lane if it is not protected."

That was Deputy Mayor Yvette Drucker at the workshop. She and council member Fran Nachlas pressed for barriers, and city staff discussed flexible posts as a possible middle ground. FDOT's current project description calls for separated bike lanes. According to The Coastal Star, cyclists will be divided from cars by 2 feet of raised concrete and 2 feet of sod, with another 4 feet of sod between the bike lane and the sidewalk.

Compared with today, the change is large. The southern stretch currently has 6-foot sidewalks and 4-foot bike lanes with no buffer, The Coastal Star reported. The new sidewalks will be 11 feet wide. Sources disagree on the new bike lane width. FDOT's project page says 7 feet, and The Coastal Star's September 2026 article says 5 feet. FDOT is the agency building the project, so its figure is the one to rely on for now.

FDOT told WFLX that the design came out of the 2018 US-1 Multimodal Corridor Study, which looked at traffic demand projected to 2040 along with safety. At FDOT's June 2025 public meeting, attendees generally supported safer crossings and bike facilities. A downtown planner also asked that trees and shade be preserved. In the Sun Sentinel's coverage, resident Joanne Wilson said passing trucks and buses had buffeted her on Federal Highway, and that she had been avoiding that stretch.

The north end, where the fall calendar happens

The northern half keeps its two lanes each way and also gets one of the project's most noticeable additions: a new signalized mid-block crosswalk with brighter lighting south of Plaza Real. Plaza Real runs through Mizner Park, and much of downtown's fall programming takes place within a few blocks of it.

  • October 1 and November 5, 6 to 9 p.m. The Night Market returns to Sanborn Square, 72 N. Federal Highway, with local artists, makers and music. The city is offering free BocaConnect rides for the event.
  • Thursday evenings, starting now. The Boca Raton Museum of Art at 501 Plaza Real is open until 8 p.m. on Thursdays and plans to add late hours on Wednesdays. Director Ena Heller told TAPinto the goal is to let people visit after work, not just on Saturdays.
  • November 7. The museum's fall season opens with "Tobi Kahn: Quest for the Essence" and "Spiritual Ecologies: Art, Nature, and Community." "Between Detachment & Devotion: On the Paradoxes of War" follows on November 21.
  • November 11, 4 to 7 p.m. Red, White & Boca at Mizner Park Amphitheater, 590 Plaza Real, features live music, a classic-car show and a Veterans Marketplace. Admission is free.
  • November 21, 6 to 10 p.m. The free holiday tree lighting at the amphitheater includes live music and food vendors.

Compare those times with the table above. On the northern segment, lane closures can start at 7:30 p.m. So you could arrive for a 6 p.m. Night Market on a fully open street and find a closed lane on the way home. The bigger risk is the drive in from the south, because closures on the lower stretch have no time limits. FDOT posts lane and sidewalk impacts each week in its Palm Beach County construction updates. The project page does not list any November closures yet.

Getting downtown without driving Federal

The city's free on-demand shuttle, BocaConnect, is the most direct way to skip the work zone. Rides are booked in the Ride Circuit app. As of July, the base service area covered downtown south of Glades Road, east of I-95, north of the Hillsboro Canal and west of NE 5th Way, SE 5th Avenue and Royal Palm Way. On the barrier island, it ran from Gumbo Limbo Nature Center to the inlet. Reported hours are 7 a.m. to 11 p.m. Monday through Thursday, 7 a.m. to 2 a.m. Friday, 9 a.m. to 2 a.m. Saturday and 9 a.m. to 11 p.m. Sunday. This summer's paid pilot zone south of the inlet, which served Waterstone Resort & Marina, was scheduled to end September 30. Plan on base-zone service only unless the city announces otherwise.

If you drive, Mizner Park's garages at the plaza's northeast and southwest corners are free, according to the city. Street parking there is metered, and valet costs extra. Every on-street space inside the CRA boundary is metered, with a four-hour limit and 24-hour enforcement. You can pay at a meter or through ParkMobile, according to a July 2026 review of downtown parking. The same review counts 112 spaces around Sanborn Square: 68 on the street and 44 in two lots.

The MiCa autonomous shuttle was running a loop inside Mizner Park this spring, TAPinto reported. At that time, an extension to Royal Palm Place was still waiting on federal approval. Check the city's current schedule before counting on MiCa to get between the two.

Around late 2027, the southern stretch of Federal Highway will have two lanes each way, buffered bike lanes, sidewalks almost twice their current width and a lit crosswalk at Plaza Real. Until then, residents will be driving through the construction on the way to dinner and events downtown. If you're wondering how a corridor change like this could affect a downtown property you own or are thinking about, Vlasek Real Estate Group would be glad to talk it through in a private conversation. Request Your Personalized Consultation.